Tempe separates a small accessory structure from a larger accessory building, and it prints fence heights. Patio covers are not given their own exemption on the permit-types page.
Call before you treat it as exempt
Patio cover, pergola, and ramada
Tempe defines a ramada or small shed at or under a published size as an accessory structure. It does not print a patio-cover exemption on the permit-types page.
Size or height threshold
Accessory structure versus accessory building
Tempe’s accessory-structure page, quoting the zoning code, says accessory structures such as ramadas and small sheds are a maximum of 200 square feet and 8 feet or less in height. A structure over that area or height is an accessory building. An accessory structure cannot sit in the required front-yard setback. It may sit in the required rear, side, and street-side setbacks if the building-code separation is provided. On a through lot it cannot be closer to the rear property line than the front-yard setback. Lot coverage still counts.
The zoning text Tempe publishes for section 3-401 says buildings over 200 square feet or over 8 feet in height are accessory buildings, such as freestanding garages, large sheds, and workshops. They cannot sit in the required front yard or street-side yard. They need at least 3 feet from side and rear property lines, plus one more foot of setback for every foot of height above 9 feet, up to 15 feet. Next to a public alley, side and rear setbacks are measured from the middle of the alley. Building-code separation still applies.
The permit-types page says a building permit is required for most tenant improvements and building construction, including fences over 6 feet and accessory or storage buildings over 200 square feet. It does not name patio covers, pergolas, or ramadas, and it does not print an exemption for them. If you are unsure, the page says to call (480) 350-8341, option 1.
The fees page, effective July 1, 2026, points to Table 1-A Building Permit Fees and Table 2-A Miscellaneous Fees. It does not print a flat patio-cover dollar amount on the web page itself. The permit-types page says plan review and permit fees vary.
Tempe prints both a permit line and yard-height limits. A single-family side or rear fence can be taller than the permit threshold only up to the zoning maximum.
Size or height threshold
Building permit
The permit-types page says a building permit is required for most building construction, including fences over 6 feet in height. It also says accessory or storage buildings over 200 square feet need a building permit. Plan review and permit fees vary.
Tempe’s fence-standards page, quoting zoning section 4-706, measures height from the highest adjacent finished ground, paving, or sidewalk within 20 feet. In a required front-yard setback the maximum is 4 feet. A use permit can allow up to 6 feet, and another 2 feet for features such as an archway or pergola, if the extra height keeps a view to the street with openings, transparent material, or a varied height. Behind the front setback, walls may be 10 feet, except single-family uses are limited to 8 feet. Corner visibility rules in section 4-702.G still apply.
The fence-height page we read does not state a swimming-pool barrier height, and it does not print a fence permit fee. It does say any wall over 6 feet needs a building permit.
A small shed can be an accessory structure with looser placement rules. Cross the size or height line and it becomes an accessory building with setbacks and a permit.
Size or height threshold
Permit line
The permit-types page says a building permit is required for accessory or storage buildings over 200 square feet. Residential submittals need a project submittal form and two complete sets of plans. Fees vary.
The accessory-structure page says a ramada or small shed at a maximum of 200 square feet and 8 feet or less in height is an accessory structure, not an accessory building. It cannot go in the front-yard setback. It may go in the rear, side, and street-side setbacks if building-code separation is met. Lot coverage still includes it.
Section 3-401, as published by Tempe, treats a building over 200 square feet or over 8 feet tall as an accessory building. The side and rear setback is at least 3 feet, plus one foot of setback for each foot of height above 9 feet, up to 15 feet. It cannot occupy the required front yard or street-side yard.
Tempe allows one attached and one detached accessory dwelling on a single-family lot, with a size cap and published setbacks. The city’s own page is also the launch page that states a build-cost range.
Rule
How many, and how big
Tempe’s ADU page says a lot that allows a single-family use and already has a single-family house may have one attached and one detached ADU. A lot of one acre or more may add one more if at least one ADU is income-restricted for households earning up to 80 percent of area median income. On lots under one acre, livable floor area is limited to 75 percent of the main house’s interior habitable area, or 1,000 square feet, whichever is less. On lots of one acre or more, the cap is 75 percent or 2,000 square feet of interior habitable area, whichever is less. District lot coverage still applies.
The same page says side, rear, and street-side setbacks are at least 5 feet unless the district or an overlay is less. The front setback matches the district’s front setback for buildings. Next to a public alley, side and rear setbacks are measured from the middle of the alley. Height is the district height, which the page says is typically 30 feet. Tempe says a December 17, 2025 Board of Adjustment decision means a two-story ADU needs a use permit. No added parking space is required, though the owner may add one. The page cites House Bill 2720 for the parking limit and for not setting ADU rules stricter than the single-family district.
Tempe’s ADU page says, according to the Angi website, national construction cost for an ADU can range from $60,000 to $225,000. It then says some local builders who spoke with staff put a high-quality ADU in Tempe at about $180,000 to $260,000. Those are the city’s citations, not a YardPermits bid. The page also says pre-approved plans, where a city offers them, were reported by other websites to save about $2,000 to $6,000. Tempe’s page does not say Tempe itself has waived review fees for a pre-approved plan.
The construction permit fee is still Table 1-A, effective July 1, 2026, not the construction-cost ranges above. The fees page does not print an ADU flat fee.
Tempe’s permit-types page does not say the city enforces CC&Rs. Association approval and the building permit are still two different approvals under state law.
Rule
State law
A.R.S. § 33-1817 says approval by a planned community association or its design committee is not a representation that the plans or the construction comply with governmental requirements. Do not treat an HOA letter as a Tempe permit, or a Tempe permit as HOA approval.
The permit-types page explains city permits and does not mention homeowners associations. If your community has architectural review, that step is outside the page Tempe published for permit types.
The fees page lists City Hall at 31 E. 5th St., Tempe, AZ 85281, the phone 480-350-4311, and [email protected] for questions about that page. It says payments are accepted in cash, check, card, and online through the citizen access portal.
Accessory or storage buildings over 200 square feet need a building permit. A structure at or under 200 square feet and 8 feet or less is treated as an accessory structure for zoning placement, and it still has to respect lot coverage and the front-yard setback.
Four feet in the required front yard, unless a use permit allows more. Eight feet for a single-family fence behind that front setback. A wall over 6 feet needs a building permit.
The city’s ADU page cites Angi for a national range of $60,000 to $225,000 and says local builders who spoke with staff put a high-quality Tempe ADU around $180,000 to $260,000. That is not a permit fee. Permit fees are in Table 1-A.
Quote requests are turned off. This page does not collect your project, does not store a form